Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.


Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.

Figure 1 – Abra ball mill installation (photo: 10 August).

Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises

$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.

Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.

Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).

In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.

Owners' costs and contingencies remain within budget.

Figure 3 – Abra TSF construction.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

MAG Announces First Quarter 2024 Production From Juanicipio

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") reports production from Juanicipio (56% 44% Fresnillo plc ("Fresnillo") and MAG, respectively) for the first quarter ("Q1") ended March 31, 2024.

Q1 Highlights

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and coins.

Silver Price Update: Q1 2024 in Review

2023 was a relatively lackluster year, silver largely traded on volatility between US$22 and US$25 per ounce.

The white metal started 2024 with less volatility and remained rangebound for the first eight weeks. Silver dropped to US$22.08 per ounce on January 21, marking its quarterly low.

Silver started seeing gains in March with the expectation that the US Federal Reserve was getting closer to lowering interest rates. Improving sentiment gave the precious metals markets momentum, causing silver to reach its quarterly high of US$25.62 on March 20, before continuing on to an 11 year high of US$29.26 on April 12.

Keep reading...Show less

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos . All dollar ($) references in this news release are United States dollars.

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and price chart.

Silver Due to Record Second Highest Deficit in 20 Years

Industrial demand for silver rose to a new record high in 2023, coming in at 654.4 million ounces (Moz).

The surge was fueled by significant advancements in green economy sectors, particularly photovoltaics (PV), where demand skyrocketed by 64 percent year-on-year to hit 195.3 Moz, surpassing previous estimates.

PV is included in the electrical and electronics segment, which experienced demand growth of 20 percent year-on-year.

Keep reading...Show less

Endeavour Silver Celebrates Milestone: Terronera Surpasses 50% Construction Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) announces a significant milestone in the construction of its new Terronera mine, in Jalisco state, Mexico. The project has surpassed the 50% completion mark, marking a crucial step forward in the Company's expansion efforts.

To celebrate this achievement, the Company is pleased to provide a short video offering investors an exclusive look at the new mine with insights from the executive team. This video highlights the construction progress, showcases the scale and scope of the project, and emphasizes the positive impact on both the company and the local community. Investors, stakeholders, and the public are invited to watch this milestone video here . The video was filmed in mid-March and represents construction progress at that time.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×