Abra Construction 83% Complete At End Of August

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 83% complete as of 31 August 2022. The arrival of the flotation cells and regrind mill to Australia completes the arrival of all the key construction equipment coming from overseas suppliers.

Managing Director, Tony James commented, “With the flotation cells and the regrind mill landing in Australia, all the key pieces of equipment required for Abra processing facility have arrived. On site, construction activities have now past 83% with focus at the plant shifting to installation of the remaining mechanical items, piping and electrical installation. Operational readiness activities continue as the site prepares to start some early dry commissioning activities. It’s also pleasing to see the TSF earthworks essentially completed and the power station reaching 94% completion”.

Figure 1 – Abra plant screening and materials handling (photo: 9 September).

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 90% complete. All key overseas supplied equipment itemised in the regular project updates shown in table 1 below have arrived in Australia. All the items in table 1 are shown as “strike-out” for completion purposes.

Table 1 – Key equipment order and delivery schedule from overseas suppliers.

Mine decline development continued in the East Decline during August. A total of 242 metres was developed with the decline reaching 1,337mRL. The decline location is 213m vertically below the surface and approximately 24m vertically above the orebody.

During August the primary ventilation raise drill pilot hole reached the 1,390mRL and back- reaming of the 6m diameter hole commenced.

In August, 15 new underground diamond drill grade control holes were completed (2,141m). Assays from the holes drilled in July are expected to be returned in September for evaluation. The second underground drill is also scheduled to commence drilling in early September, following installation of the required power services.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Klondike Silver Announces Private Placement

Klondike Silver Announces Private Placement

Klondike Silver Corp. (the “Company”) (TSX.V: KS) The Company announces that it is raising up to $1,500,000 through a non-brokered private placement (the “Offering”) of up to 30,000,000 units at a price of $0.05 per unit. Each unit will consist of one common share and one share purchase warrant, with each warrant exercisable for a period of 5 years from the closing at a price of $0.05 per share in year one and two then $0.08 per share in years three, four and five. All Units are subject to a four-month hold period from the date of issuance. Commissions may be paid on a portion of the funds raised. The Offering is subject to TSX Venture Exchange ("TSXV") final acceptance.

Keep reading...Show less

Endeavour Silver Announces First Drawdown on The Terronera Senior Secured Debt Facility

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce the first drawdown of $60 million of the $120 million senior secured debt facility (the " Debt Facility ") for the development of the Terronera Mine in Jalisco state, Mexico. The debt facility is provided by Société Générale and ING Bank N.V. and closed last year (see news release dated October 10, 2023 ). All references to dollars ($) in this news release are in United States dollars.

Construction of the Terronera mine is well underway and remains on track and has satisfied all conditions precedent to first draw. Key terms of the Debt Facility remain consistent with those previously announced in the Company's news release dated April 18, 2023 and the hedge contract terms have now been executed, further reducing financial risk in the project. The key terms of these contracts are as follows:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Pan American Silver to Announce First Quarter 2024 Unaudited Results and Host Annual General and Special Meeting of Shareholders on May 8

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) (" Pan American ") will announce its unaudited results for the first quarter of 2024 after market close on Wednesday, May 8, 2024. Pan American will also be holding its Annual General and Special Meeting of shareholders (the "Shareholders Meeting") the same day at 3:00 pm PT.

First Quarter 2024 Unaudited Results Conference Call and Webcast

News Provided by Business Wire via QuoteMedia

Keep reading...Show less

Endeavour Silver Delivers Strong Production in Q1 2024

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to report first quarter 2024 production of 1,460,006 silver ounces (oz) and 10,133 gold oz, for silver equivalent (1) ("AgEq") production of 2.3 million oz.

"Across our portfolio, the operations performed largely in-line with our expectations to deliver our annual production guidance of 8.1- 8.8 million silver equivalent ounces in 2024," commented Dan Dickson, Chief Executive Officer. "The infrastructure upgrades in pumping and ventilation have stabilized production at Guanacevi, and the impact from these improvements is being realized by our strong start to the year. Gold and silver prices have strengthened considerably, which will improve future revenues. I look forward to building upon the success of this quarter."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Rows of silver bars with two lying on top of them.

ASX Silver Stocks: 5 Biggest Companies in 2024

As a precious metal, silver is often compared to gold, and similarly holds an important role in the production of jewellery and as a safe-haven investment. However, silver also has increasing industrial uses.

In addition to its applications in jewellery and silverware, the white metal is becoming important for its use in the energy transition, specifically for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels. It also has a wide array of uses in the production of electronics, automobiles, medicine and photography.

Despite its important role, silver is still largely a secondary metal, being mined as a by-product of lead, gold, zinc and copper. There are, however, several Australian companies that have put silver first.

Keep reading...Show less

Fortuna reports strong gold equivalent production of 112,543 ounces in the first quarter of 2024

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) reports strong gold and gold equivalent production for the first quarter of 2024 from its five operating mines in West Africa and Latin America. Gold and silver production for the quarter was 89,678 ounces and 1.1 million ounces, respectively, or 112,543 gold equivalent ounces 1 including lead and zinc by-products.

Fortuna reiterates its 2024 annual production guidance range of 343 to 385 thousand ounces of gold and 4.0 to 4.7 million ounces of silver or between 457 and 497 thousand ounces of gold equivalent ounces 2 , including lead and zinc by-products (refer to Fortuna news release dated January 18, 2024 ). All amounts expressed in this news release are in US dollars unless otherwise stated.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
{{ sections }}
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×