Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.

Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.

Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.

Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).

The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

Fortuna files Form 40-F, Annual Report

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) reports that the Company has filed today its fiscal 2023 annual report on Form 40-F with the U.S. Securities and Exchange Commission (" SEC ").

The Form 40-F, which includes the Company's fiscal 2023 annual audited financial statements, management's discussion and analysis, and annual information form, is available on the Company's website and on the SEC´s website .

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

MAG Silver Announces Robust Updated Technical Report for Juanicipio

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG", or the "Company") is pleased to announce it has filed on SEDAR, the Juanicipio Mineral Resource and Mineral Reserves NI 43-101 Technical Report (the " 2024 Technical Report " or the " Report ") for the Juanicipio Mine (44% MAG, 56% Fresnillo plc, the mine operator) located in the state of Zacatecas, Mexico. The Report was prepared in accordance with the requirements of National Instrument 43-101 Standards of Disclosure for Mineral Projects (" NI 43-101 "). The Report was prepared by AMC Mining Consultants (Canada) Ltd. (" AMC ") of Vancouver, with assistance from Knight Piésold and Co. (" KP "), both independent consultants, on behalf of MAG. This Report provides an update to the "MAG Silver Juanicipio NI 43-101 Technical Report, Amended and Restated, Zacatecas State, Mexico" 2017 Technical Report by AMC. Mineral Resource and Mineral Reserve estimates are current as of May 31, 2023. The Report has an effective date of March 4, 2024.The monetary values shown in the Report are in US dollars ($) and on a 100% basis unless stated otherwise.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

First Majestic Announces Commencement of Bullion Sales from First Mint

First Majestic Silver Corp. (NYSE: AG) (TSX: FR) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the completed commissioning and commencement of bullion sales from its 100% owned and operated minting facility, First Mint, LLC ("First Mint"). Located in the State of Nevada, United States, First Mint vertically integrates a manufacturing plant for investment-grade fine silver bullion into the First Majestic portfolio.

In line with First Majestic's commitment to environmental and community stewardship, First Mint operates state-of-the-art machines that require less electricity and do not release gas emissions compared to traditional minting processes. The eco-friendly and high efficiency production line allows the mint to produce over 10% of the Company's current silver production coming from the Mexican operations. Plans are currently underway to expand the operation by adding additional equipment and personnel as required.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Silvercorp Offer for OreCorp Lapsed

Trading Symbol:
TSX: SVM
NYSE AMERICAN: SVM

Silvercorp Metals Inc. (" Silvercorp " or the " Company ") (TSX: SVM) (NYSE American: SVM) announced today that, further to its off-market takeover bid (the " Offer ") for all of the ordinary shares in OreCorp Limited (" OreCorp ") (ASX:ORR), Silvercorp did not satisfy the 50.1% minimum acceptance condition prior to the close of the Offer on March 22, 2024 and elected not to exercise its "right to match" a competing offer for OreCorp. Silvercorp will remain entitled to payment of a break fee of approximately AUD$2.8 million in certain circumstances, as set out in the BID.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

MAG Silver Provides Notice of Updated Juanicipio Technical Report

MAG Silver Corp. (TSX NYSE American: MAG) (" MAG ", or the "Company ") announces that it will release results from its updated Juanicipio Technical Report (the " Report ") on Wednesday, March 27, 2024. A conference call will be held to discuss the results of the Report on Wednesday, March 27, 2024 at 8:15 a.m. Eastern Time.

Conference call dial-in numbers:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Fortuna to present at the Gold Forum Europe 2024 in Zürich, Switzerland

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to announce that it will be attending Gold Forum Europe 2024 which is being held at the Park Hyatt in Zürich, Switzerland, from April 8 to 10, 2024.

Jorge A. Ganoza, President, Chief Executive Officer, and co-founder of Fortuna, will be presenting on Tuesday, April 9 at 2:30 p.m. Central European Time in Ballroom 3.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×