Abra Development Works Ramping Up, Major Contracts Finalised

GALENA MINING LTD. ("Galena" or the "Company") (ASX: G1A) announces that Abra Mining Pty Limited ("AMPL"), the joint-venture company for the Abra Base Metals Project ("Abra" or the "Project") has finalised significant contracts in relation to the development of the Abra lead-silver Project. Figure 1 shows Galena, Byrnecut and GRES executives inspecting the new Abra underground Jumbo supplied by Sandvik.


HIGHLIGHTS:

  • Underground mining contract finalised with Byrnecut with mobilisation in the second half of September 2021
  • Plant construction contract with GR Engineering Services Limited (ASX: GNG) in full implementation, with key long lead items ordered, FEED completed and the final detailed engineering at 15%
  • Red Dust Holdings have commenced site bulk earthworks associated with aerodrome, TSF and plant and infrastructure pads

Managing Director, Tony James commented, "A major milestone has been achieved at Abra with the finalisation of the underground mining contract with Byrnecut and the implementation of the process plant EPC with GR Engineering Services. Both companies have been very strong supporters of the project over a long period of time and its very rewarding for everyone to see the work starting on the ground.

The Byrnecut mining contract is for 4 years, with the remainder of this year and the majority of next year focussed on gaining access to the orebody, 230m below surface. During this time the mine is effectively a "single heading" decline and the manning requirements for that period are far lower than when the mine reaches commercial ore production in 2023. The actual mining work is expected to commence in the coming weeks. Equipment and labour have been sourced and are ready for mobilisation in the second half of September.


Click here for the full ASX release

G1A:AU
The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

MAG Announces First Quarter 2024 Production From Juanicipio

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") reports production from Juanicipio (56% 44% Fresnillo plc ("Fresnillo") and MAG, respectively) for the first quarter ("Q1") ended March 31, 2024.

Q1 Highlights

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and coins.

Silver Price Update: Q1 2024 in Review

2023 was a relatively lackluster year, silver largely traded on volatility between US$22 and US$25 per ounce.

The white metal started 2024 with less volatility and remained rangebound for the first eight weeks. Silver dropped to US$22.08 per ounce on January 21, marking its quarterly low.

Silver started seeing gains in March with the expectation that the US Federal Reserve was getting closer to lowering interest rates. Improving sentiment gave the precious metals markets momentum, causing silver to reach its quarterly high of US$25.62 on March 20, before continuing on to an 11 year high of US$29.26 on April 12.

Keep reading...Show less

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos . All dollar ($) references in this news release are United States dollars.

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and price chart.

Silver Due to Record Second Highest Deficit in 20 Years

Industrial demand for silver rose to a new record high in 2023, coming in at 654.4 million ounces (Moz).

The surge was fueled by significant advancements in green economy sectors, particularly photovoltaics (PV), where demand skyrocketed by 64 percent year-on-year to hit 195.3 Moz, surpassing previous estimates.

PV is included in the electrical and electronics segment, which experienced demand growth of 20 percent year-on-year.

Keep reading...Show less

Endeavour Silver Celebrates Milestone: Terronera Surpasses 50% Construction Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) announces a significant milestone in the construction of its new Terronera mine, in Jalisco state, Mexico. The project has surpassed the 50% completion mark, marking a crucial step forward in the Company's expansion efforts.

To celebrate this achievement, the Company is pleased to provide a short video offering investors an exclusive look at the new mine with insights from the executive team. This video highlights the construction progress, showcases the scale and scope of the project, and emphasizes the positive impact on both the company and the local community. Investors, stakeholders, and the public are invited to watch this milestone video here . The video was filmed in mid-March and represents construction progress at that time.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

Ă—