See our exclusive index of companies on the move:
Explore Stocks- Top Stocks
- Top Australian Gold Stocks
- Top ASX Copper Stocks
- Top ASX Nickel Stocks
- Top ASX Rare Earth Stocks
- Top Battery Metals Stocks on the ASX
- Top Australian Lithium Stocks
- Top Graphite Miners on the ASX
- 10 ASX Cannabis Stocks
- Top ASX Tech Stocks
- Top AI Stocks on the ASX
- On Site
- About Australian Cannabis Investing
- About Australian Resource Investing
- About Australian Tech Investing
- About Australia Investing
- Of Interest
- ASEAN-Australia-New Zealand Trade Agreement
- Association of Southeast Asian Nations (ASEAN)
- Australian FAQ on ASEAN
- Australia Government on Foreign Investments
Altura Mining has revised its production guidance for the December quarter following changes to maintenance schedules.
Altura Mining (ASX:AJM) has revised its production guidance for the December quarter following changes to maintenance schedules to bring forward a plant shutdown previously planned for February 2020.
As quoted in the press release:
The 94-hour shutdown was accelerated to enable replacement of components on the process plant’s grinding circuits following assessment by the operations team and risk mitigation strategy. The shutdown was successfully completed with replacement components performing as planned. In addition, during the December quarter, production was negatively affected by lower than forecast crusher performance, which reduced plant throughputs and required feed of stockpiled crushed ore with higher quality variability.
Fines production through the flotation circuit also was interrupted by various initiatives that were trialled as part of Altura’s continuous improvement plan which is primarily aimed at increasing lithia recovery rates.
As a result, production in the quarter is now expected to total approximately 45,000 – 50,000 wet metric tonnes (wmt) (previous guidance 53,000 – 57,000 wmt). Sales for the December quarter are expected to reach approximately 40,000 dry metric tonnes (dmt) (previous guidance 50,000 – 55,000 dmt) following the delayed departure of a cargo previously planned for December 2019. The cargo is now likely to load and depart in January 2020 as part of a larger shipment of approximately 22,000 dmt.
James Brown, managing director, commented:
The plant continues to perform reasonably well as we focus on maintaining a stable production profile coupled with delivery of a consistent product with a lower cost base. The market remains subdued but we remain confident that the long term market fundamentals of our business and the outlook for the lithium market itself remains very positive. We have been maintaining a regular product delivery schedule and working with our buyers in order to adapt to their needs.
Click here to read the whole Altura Mining (ASX:AJM) press release.