Kalium Lakes predicts commissioning and ramp up to the Western Australia-based project’s nameplate throughput will take place by 2020.

Kalium Lakes (ASX:KLL) has completed a bankable feasibility study (BFS) for its Beyondie sulfate of potash (SOP) project. The report includes an update to the asset’s ore reserves.

The BFS points to a higher production rate than expected at 164 kilotons per annum — that’s 10 percent higher than the amount shown in the project’s prefeasibility study (PFS). It also adds an extra seven years to Beyondie’s anticipated mine life compared to the PFS, putting it in excess of 30 years.

In terms of Beyondie’s ore reserves, they have grown by 90 percent, with proven and probable reserves totaling 5.14 million tonnes of SOP and 12,400 milligrams per liter of potassium sulfate. Meanwhile, its mineral resource is 19.6 million tonnes of SOP at 12,434 milligrams per liter of potassium sulfate.

The project was also able to improve its financial outcomes through the BFS. Its pre-tax NPV stands at AU$575 million, while its IRR is 20 percent. Its average earnings before interest, tax, depreciation and amortization are AU$116 million per year, with a payback period of seven years.

Kalium’s managing director, Brett Hazelden, spoke about how the positive BFS results have helped speed up the progress of early works at the project.

“As a result of the extensive detail delivered in the BFS report, the exceptional financial outcome, and the positive engagement with financial institutions, the board has now endorsed the commencement of early works and final engineering,” Hazelden said in a statement.

“This will allow us to complete the critical path activities associated with the timely construction of the project including, most importantly, the road upgrades and accommodation facility,” he added.

The company predicts that commissioning and ramp up to the Western Australia-based project’s nameplate throughput will take place by 2020.

Kalium has collaborated with German fertilizer producer and distributor K+S (ETR:SDF) on a 10-year offtake agreement for Beyondie. The agreement will entail Kalium supplying 75,000 tonnes of SOP per year to K+S, with K+S lending expertise and technical support as part of its contribution.

Kalium’s share price closed Wednesday (September 18) at AU$0.46, up 15.19 percent year-to-date.

Don’t forget to follow us @INN_Resource for real-time updates!

Securities Disclosure: I, Olivia Da Silva, hold no direct investment interest in any company mentioned in this article.

Hastings Technology Metals Ltd Measured and Indicated Mineral Resource Tonnes Up by 54%

Perth, Australia (ABN Newswire) – Australia’s next rare earths producer, Hastings Technology Metals Ltd (ASX:HAS) (FRA:5AM), is pleased to announce a material increase in Mineral Resource Estimate at its Yangibana Rare Earths Project (Yangibana) in Western Australia’s Gascoyne region.

Highlights

– Measured and Indicated Mineral Resource tonnes increased by 54% to 16.3Mt for Yangibana deposits drilled during 2020.

Keep reading... Show less

ASI certifies Rio Tinto’s ISAL smelter for responsible production

Rio Tinto’s ISAL smelter in Iceland has been certified by the Aluminium Stewardship Initiative (ASI) for meeting the highest internationally recognised standards for responsible aluminium production.

The certification continues Rio Tinto’s leadership of the industry on responsible aluminium production from mine to metal, and means customers can be assured aluminium produced at ISAL meets independent environmental, social and governance standards.

Keep reading... Show less

Rio Tinto updates details of tailings facilities

Rio Tinto today released updated information in relation to its global tailings facilities to align with the requirements of the Global Industry Standard for Tailings Management (GISTM) released in August 2020, an initiative co-convened by the International Council on Mining and Metals, United Nations Environment Programme and the Principles for Responsible Investment.

The latest disclosure at http://www.riotinto.com/tailings builds on previously disclosed information on each of Rio Tinto’s global tailings facilities released in June 2019 and the publication of Rio Tinto’s Group Procedure and updated Standard for ‘Management of tailings and water storage facilities’ in February 2019. The changes to existing data are in line with guidance contained in GISTM including updating information previously disclosed.

Keep reading... Show less

Hastings Technology Metals Ltd Quarterly Activities Report

Perth, Australia (ABN Newswire) – Australia’s next rare earths producer, Hastings Technology Metals Ltd (ASX:HAS) (FRA:5AM) is pleased to report on exploration and development activities for the three-month period to 31st March 2021. Most of the activity focused on the Company’s Yangibana Rare Earths Project (“Yangibana”) in the Gascoyne region of Western Australia.

Highlights

– Hastings raised $100.7 million (before costs) through a two-tranche equity placement priced at $0.19 per share, with funds to be used to advance development of the Yangibana Rare Earths Project.

Keep reading... Show less

Argyle Diamond Mine Closure: What’s Next for the Sector in Australia?

Click here to read part one of this article, which covers the closure of the Argyle diamond mine.

When the mining equipment permanently shut down at Western Australia's Argyle mine in November 2020, the country's diamond sector entered a transitional period.

As the world's fourth largest diamond-producing asset shuttered, domestic output of the gems instantly declined by as much as 90 percent.

Keep reading... Show less