Blackstone Minerals Limited (“Blackstone” or the “Company”) is pleased to inform investors that mining activities have recommenced at the Company’s 90% owned Ta Khoa Nickel Project in northern Vietnam.


Using a combination of Australian and Vietnamese mining professionals and operators, Blackstone will:

  • Complete ~1,000m of development through the Ban Phuc disseminated orebody generating nickel ore representative of the life of mine plant feed.
  • Recommission the Ban Phuc Nickel Concentrator to produce two batches of Nickel Concentrate for use in the Ta Khao Refinery piloting programs.
  • Deliver the first batch of concentrate to Perth for treatment by ALS Laboratories in the first phase piloting program.
  • Process and store the second batch for use in the second phase pilot plant which will be built in Son La in 2022.

Figure 1 – Ta Khoa Management Team and the Underground Mining Contractor outside the Ban Phuc Portal

Click here for the full ASX Release

This article includes content from Blackstone Minerals, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

BSX:AU

Top News

Related News

×