Toro Energy Limited (ASX: TOE) (‘the Company’ or ‘Toro’) is pleased to announce that the scoping level capital expenditure (CAPEX) estimation for its proposed stand-alone Lake Maitland Uranium-Vanadium operation has now been completed by mining engineers at SRK Consulting Australasia (SRK) and metallurgical and processing engineers at Strategic Metallurgy.

HIGHLIGHTS

  • Scoping level estimation of CAPEX for the proposed stand-alone Uranium-Vanadium operation at Lake Maitland has been completed by SRK Consulting Australasia and Strategic Metallurgy.
  • Entire proposed operation is estimated to have a total build price of AUS$270 million or US$202.5 million (based on a US$:AUS$ 0.75 exchange rate), inclusive of a 20% contingency and 15% allowance for engineering, procurement and construction management (EPCM).
  • New CAPEX estimate delivers a AUS$45 million reduction compared to the estimation of AUS$315 million for the entire Wiluna Uranium operation with processing based at the Centipede-Millipede deposit, undertaken almost 10 years ago (see ASX announcement of 30 January 2014).
  • Latest CAPEX estimation includes all infrastructure for the proposed stand-alone Lake Maitland Uranium-Vanadium operation, inclusive of the entire processing facility with beneficiation plant and the ability to produce both a uranium and vanadium product, all mining and administration related infrastructure, access roads, power plant, borefield and a reverse osmosis desalinisation plant for water supply.
  • Estimated that total processing infrastructure will have a build cost of AUS$133 million (or AUS$95.8 million excluding contingency and EPCM) and the total non-processing infrastructure will have a build cost of AUS$137 million (or AUS$99.2 million excluding contingency and EPCM).
  • Proposed stand-alone Lake Maitland Uranium-Vanadium operation will have a mine life of approximately 17 years, will process some 1.94 Mt of ore per annum (front of beneficiation plant) and will produce approximately 23.5 million pounds (Mlbs) of U3O8 and 12.2 Mlbs of V2O5 over its 17 year life (the latter calculation is still being adjusted around C11operating expenditure (OPEX) calculations).
  • SRK is currently estimating the overall and year by year OPEX based on the proposed new mining schedule that resulted from the recently completed re-optimisation of the Lake Maitland mining pit. This OPEX estimation is expected to be completed soon.
The total CAPEX for the Lake Maitland mining and processing operation has been estimated at AUS$270 million or US$202.5 million (assuming a US$:AUS$ 0.75 exchange rate) inclusive of a 20% allowance for contingency and 15% allowance for EPCM.

Toro is pleased to highlight that this CAPEX estimate is AUS$45 million less than the previous CAPEX estimate of AUS$315 million, which was for the entire Wiluna Uranium operation with processing based at the Centipede-Millipede deposit, despite the latter being estimated almost 10 years ago (see ASX release of 30 January 2014).

Commenting on Toro’s CAPEX estimate for a proposed stand-alone Lake Maitland Uranium- Vanadium operation, Toro’s Executive Chairman, Richard Homsany, said:

“We are delighted to release a very competitive US$202.5 million CAPEX estimate for our proposed Lake Maitland Uranium-Vanadium operation. After the outstanding pit re-optimisation results, the CAPEX estimate is an excellent and economically significant milestone towards delivering our strategy to advance the Wiluna Uranium Project so that it is optimised when conditions are favourable for its financing and construction.

The Wiluna Uranium Project is an asset of global significance, and our clear focus is on the long-term feasibility of uranium production from the asset as global uranium markets continue to strengthen. Toro’s view is that we are in the early stages of an increasingly upward uranium market with peak uranium prices still to come.

Toro has invested significantly in the Wiluna Uranium Project and through our patient and focussed approach our team has delivered significant potential improvements in both the capital and operating costs of the entire Wiluna Uranium Project.

Lake Maitland represents a significant proportion of the Wiluna Uranium Project’s resources of both uranium and vanadium. The US$202.5 million CAPEX for Lake Maitland compared to the CAPEX estimation of AUS$315 million for the entire Wiluna Uranium Project prepared almost 10 years ago is an outstanding result given inflationary pressures, and significantly improves the economics of the entire project.

This CAPEX estimate is a key milestone that demonstrates that Lake Maitland could itself be a viable stand-alone uranium-vanadium operation over an approximate 17 year mine life, processing 1.94 Mt of ore per annum (front of beneficiation plant) and producing approximately 23.5 Mlbs of U3O8 and 12.2 Mlbs of V2O5.

This is an exciting result for Toro shareholders. Further optionality and economic upside exists for Toro given the proximity to Lake Maitland of the Centipede, Millipede and Lake Way uranium deposits that could increase the production of uranium and vanadium. We look forward to announcing the C1 operational expenditure estimate from the scoping study, which is expected to be completed soon.”


Click here for the full ASX release

This article includes content from Toro Energy Ltd, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

TOE:AU
Toro Energy

Toro Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Toro Energy

Toro Energy


Keep reading...Show less

Ur-Energy Announces Appointment of Vice President Regulatory Affairs

Ur-Energy Inc. (NYSE American:URG)(TSX:URE) (the "Company" or "Ur-Energy") is pleased to announce the appointment of Ryan S. Schierman as Ur-Energy's Vice President Regulatory Affairs

Ur-Energy Chairman and CEO, John Cash, stated, "We are pleased to expand our executive team with the addition of Ryan Schierman as our Vice President Regulatory Affairs. Ryan is highly respected as a former regulator and well known in our industry as a true professional with great expertise in regulatory compliance and environmental health and safety matters. Ryan joins us to lead our well-established EHS department as Ur-Energy moves ahead with our Shirley Basin ISR facility and we look forward to additional growth throughout the Company."

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less

Global Atomic Announces 2023 Results and publishes Dasa Uranium Project Feasibility Study

Dasa Uranium Project Remains on Schedule to Produce Yellowcake in Q1 2026

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced today its operating and financial results for the year ended December 31, 2023 .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Denison Announces Signing of Sustainable Communities Investment Agreement

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ("Denison") (TSX: DML) (NYSE American: DNN) is proud to announce the signing of a Sustainable Communities Investment Agreement (the "Agreement") with the municipalities of the Northern Village of Beauval the Northern Village of Île-à-la Crosse, the Northern Hamlet of Jans Bay and the Northern Hamlet of Cole Bay (the "Communities"). View PDF version

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Text saying "Uranium Night" superimposed over band playing music.

Uranium Night at PDAC Raises $10,000 for Charity

At this year’s Uranium Night at the Prospectors & Developers Association of Canada (PDAC) convention, the event's sponsors secured a $10,000 donation for the charity Haven Family Connections.

With the uranium sector having its hottest season in years, there was much to celebrate at the event, which was held on March 4 at the Lucky Clover Irish Pub in Toronto. Early in the year, the uranium spot price broke through the US$100 per pound level for the first time since 2007, rising to a 16 year high of US$106 as demand continued to outpace supply.

Although the price has since pulled back to the US$90 level, industry experts still predict a bright future for the energy commodity as countries around the world pursue nuclear power as a strategy for meeting clean energy goals.

Keep reading...Show less

Laramide Outlines 2024 Australian Exploration Plans

Laramide Resources Ltd. ("Laramide" or the "Company") (TSX: LAM) (ASX: LAM) (OTCQX: LMRXF) is pleased to announce 2024 work plans for Australia which include a large drill campaign of up to 12,000m across multiple targets at the Westmoreland Uranium Project in NW Queensland and into the Murphy Uranium Project in the Northern Territory. Two drill rigs have been secured and logistical plans are well advanced for a campaign that will build on last year's successful exploration effort which saw 40 holes completed across 4,000 cumulative meters. Drilling is expected to commence in approximately 6-8 weeks' time at the conclusion of the current wet season.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
C29 Metals

C29 Acquires Transformative High-Grade Uranium Project

C29 Metals Limited (ASX:C29) (C29, or the Company) is pleased to announce it has entered into a binding share sale and purchase agreement (Acquisition Agreement) with CA Metals Pty Ltd (CA Metals) and Ulytau Resources Ltd (Ulytau Resources) to acquire a 100% legal and beneficial interest in a granted exploration licence located in Kazakhstan (Ulytau Uranium Project).

Keep reading...Show less
Toro Energy

Toro Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×