Gruyere Produces First Ore, Remains on Schedule

The Gruyere gold project, a joint venture between Gold Road Resources and Gruyere Mining Company, has produced its first ore on schedule.

The Gruyere gold asset, a joint venture (JV) between Gold Road Resources (ASX:GOR) and Gruyere Mining Company, a subsidiary of Gold Fields (NYSE:GFI), has produced its first ore on time.

According to a joint statement from the JV partners, construction on Gruyere’s processing plant and infrastructure is over 91 percent complete. Contractor Downer EDI (ASX:DOW) began double-shift operations as part of mining production ramp up.

Construction in the project’s primary crusher area is “substantially” complete, while ore commissioning of the primary crusher to coarse ore stockpile circuit is currently in progress.

The last pieces of construction to be completed are in the milling, CIL and elution areas, which include piping, electrical and instrumentation installations, along with system and equipment commissioning.

The companies said a significant amount of ore is to be stockpiled to de-risk the project leading up to first gold production, which is scheduled to take place in the June 2019 quarter. Gruyere remains on schedule in terms of production and within its estimated cost estimates.

Located approximately 200 kilometers east of Laverton in Western Australia, Gruyere has a mineral resource of 144 million tonnes grading 1.3 grams per tonne for 5.9 million ounces of contained gold. The project was discovered by Gold Road in 2013, and in November 2016 the company sold a 50-percent stake to Gold Fields for AU$350 million.

Gold Fields manages the project and the mine’s operations, while Gold Road holds responsibility for exploration on the JV tenements.

The project, which began construction in 2017, is expected to produce 85,000 to 120,000 ounces of gold during 2019, and is anticipated to hit 300,000 ounces annually upon reaching steady state production.

Gold Road’s share price closed 5.76 percent higher on Tuesday (January 29), ending the day at AU$0.735.

Don’t forget to follow us @INN_Resource for real-time updates!

Securities Disclosure: I, Olivia Da Silva, hold no direct investment interest in any company mentioned in this article.

Torian Resources Limited Significant Gold Results from Surface at Mt Stirling

Perth, Australia (ABN Newswire) – Torian Resources Ltd (ASX:TNR) is pleased to advise that recent drilling results continue to extend the Mt Stirling Gold System over ~1.1km of Strike, ~300m at depth, and it remains open in multiple directions.

Highlights:

– The interpreted strike of the Mt Stirling gold system exceeds 1.160km with Mt Stirling Main Zone; Hanging Wall and Viserion lodes all remaining open along strike and down-dip.

Keep reading... Show less

eMetals Limited Updates Shareholders On Exploration – April 12, 2021

eMetals Limited (ASX:EMT) (eMetals or Company) is pleased to update shareholders on exploration activities which have commenced across the Company’s projects.

HIGHLIGHTS

Keep reading... Show less

Discovery Harbour Provides Newcrest’s Planned Program for Fortuity 89, Nevada

Discovery Harbour Resources Corp. (TSXV: DHR) (OTC Pink: DCHRF) (FSE: 4GW) (the “Company” or “Discovery Harbour”) is pleased to announce that Newcrest Resources Inc., a wholly owned subsidiary of Newcrest Mining Limited (“Newcrest”), has provided the details of its planned program for the Fortuity 89 epithermal gold property in Nevada.

The Fortuity 89 property covers very limited outcrop surrounded by a large covered area. The outcrop and interpreted geology are prospective for concealed low sulphidation epithermal gold mineralization below shallow unconsolidated alluvial gravels. Newcrest’s planned activities include a geophysical program encompassing a 675 line kilometre drone airborne magnetic survey, a 250 station ground gravity survey and a 45 line kilometre audio band magnetotellurics (AMT) resistivity survey. It is intended that geologic and alteration sampling and mapping will also be undertaken with a soil geochemical sampling program. The intended outcome of this program is to identify potential drill targets for testing this calendar year.

Keep reading... Show less

Blackdome-Elizabeth Gold Project 2021 Exploration Plan and Update

Tempus Resources Ltd. (“Tempus” or “the Company”) (ASX:TMR)(TSXV:TMRR) is pleased to provide an update on the exploration plan for the upcoming field season at the Blackdome-Elizabeth Gold Project, located in British Columbia, Canada

The 2021 exploration program at Elizabeth and Blackdome is fully permitted and on schedule to commence at the end of Q2, 2021. The program will consist of 7,500 metres of down plunge and along strike diamond drilling at Elizabeth to expand the known gold mineralisation, in parallel with detailed alteration and mapping studies at Blackdome in support of future resource expansion drilling.

Keep reading... Show less

Rio Tinto reaches agreement with Turquoise Hill Resources on financing plan for Oyu Tolgoi

Rio Tinto has entered into a binding Heads of Agreement (HoA) with Turquoise Hill Resources (TRQ) for an updated funding plan (the “Funding Plan”) for the completion of the Oyu Tolgoi (OT) Underground Project in Mongolia. The Funding Plan addresses the estimated remaining known funding requirement of approximately $2.3 billion 1 , building on and replacing the arrangements established in the Memorandum of Understanding that Rio Tinto and TRQ previously entered into on 9 September, 2020.

Under the HoA, subject to securing approval by OT LLC and any required support from the Government of Mongolia, and subject to timing, availability, and terms and conditions being acceptable to both parties, Rio Tinto and TRQ will:

Keep reading... Show less

Top News

Related News