King Island Scheelite Provides Tungsten Project Update

During 2018, King Island’s primary focus at the Dolphin project was the construction of a new processing plant.

Critical metals developer King Island Scheelite (ASX:KIS) released an update for its ongoing redevelopment efforts at the solely-owned Dolphin tungsten project on King Island, Tasmania.

During 2018, King Island’s primary focus for the Dolphin project was the construction of a new processing plant designed to treat ore produced from the Dolphin mine.

Production ceased at the Dolphin mine in 1992 due to depressed tungsten prices. King Island is currently implementing its redevelopment strategy for the mine amid steady, yet restrained tungsten prices.

One of the key components to the redevelopment of the site was design and cost analysis of the proposed processing plant. King Island looked to Gekko Systems to design the facility.

Gekko was tasked with designing a plant capable of treating the ore from the Dolphin mine, based on metallurgical test work completed at the ALS laboratory in Tasmania.

The proposal from the plant design company was completed in mid-December.

“A modular design was preferred as this will minimize construction and commissioning times on site and result in reduced costs,” Johann Jacobs, King Island chairman said in the announcement.

“Capital and operating costs are significantly lower than those determined in previous feasibility studies, due largely to the re-design of the flow sheet.”

Using the proposed modular design, it is estimated that procurement, construction and commissioning could be feasible within a twelve-month period.

The relocation of the processing plant from its previous position is also part of the larger redevelopment.

In order to move the plant from the eastern side of the pit to the western, the company sought approval from the King Island Council. After consulting with the Tasmanian Environmental Protection, the King Island Council granted the planning permit approval.

“The new site has significant operational advantages over the previous site, in terms of reduced environmental impact (noise and visual), vehicle accessibility, proximity to the Grassy Port, reduced civil work costs and a much safer environment for light vehicles,” added Jacobs.

A detailed mine plan and schedule for the Dolphin project allows for eight years of open cut mining at an average rate of 400,000 tonnes per year of ore.

Shares of King Island were up 6 percent on Monday (January 21), trading at AU$0.08.

Don’t forget to follow us @INN_Resource for real-time updates!

Securities Disclosure: I, Georgia Williams, hold no direct investment interest in any company mentioned in this article.

Rio Tinto reaches agreement with Turquoise Hill Resources on financing plan for Oyu Tolgoi

Rio Tinto has entered into a binding Heads of Agreement (HoA) with Turquoise Hill Resources (TRQ) for an updated funding plan (the “Funding Plan”) for the completion of the Oyu Tolgoi (OT) Underground Project in Mongolia. The Funding Plan addresses the estimated remaining known funding requirement of approximately $2.3 billion 1 , building on and replacing the arrangements established in the Memorandum of Understanding that Rio Tinto and TRQ previously entered into on 9 September, 2020.

Under the HoA, subject to securing approval by OT LLC and any required support from the Government of Mongolia, and subject to timing, availability, and terms and conditions being acceptable to both parties, Rio Tinto and TRQ will:

Keep reading... Show less

Rio Tinto Exploration and Calibre Mining Initiate 2021 Exploration Program Including 5,500 Metre Drilling Campaign Prioritizing Prospective Near-Surface Copper and Copper-Gold Mineralization

Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) (the “Company” or “Calibre”) is pleased to provide an update on the Borosi exploration project held under an earn-in option agreement between Rio Tinto Exploration (LSE:RIO) (“RTX”) (“Rio Tinto”) and Calibre. Calibre controls a 100% interest in the Borosi concessions located in the prolific Mining Triangle region of northeastern Nicaragua. RTX has the right to earn a 75% interest by spending US$45 million over eleven years in the project ( see Calibre news release dated February 24, 2020 ). The Borosi exploration program is being directed by RTX through a partnership agreement with Calibre as project operator.

Highlights

Keep reading... Show less

FDA Approves Trodelvy®, the First Treatment for Metastatic Triple-Negative Breast Cancer Shown to Improve Progression-Free Survival and Overall Survival

Trodelvy Significantly Reduced the Risk of Death by 49% Compared with Single-Agent Chemotherapy in the Phase 3 ASCENT Study –

– Trodelvy is Under Regulatory Review in the EU and in the United Kingdom, Canada, Switzerland and Australia as Part of Project Orbis

Keep reading... Show less

Rio Tinto details $47 billion 2020 economic contribution, including $8.4 billion of taxes and royalties

Rio Tinto today released its 2020 Taxes paid: Our economic contribution report , which shows the company made a total direct economic contribution of $47 billion in the countries and communities where it operates, including $8.4 billion of taxes and royalties.

Despite the widespread challenges of COVID-19 in 2020, the contribution was up from the previous year, when Rio Tinto made a total direct economic contribution of $45.1 billion in the countries and communities where it operates, including $7.6 billion of taxes and royalties.

Keep reading... Show less

Top News

Related News