Energy Resources’ Ranger Closure and Rehab Costs to Rise

Energy Resources’ Ranger Closure and Rehab Costs to Rise

Energy Resources of Australia has finalized its closure feasibility study for the rehabilitation of the Ranger uranium project area.

Energy Resources of Australia (ASX:ERA) has finalized its closure feasibility study (FS) for the rehabilitation of the Ranger uranium project area in the Northern Territory.

The company announced on Friday (February 8) that its board has approved the FS and recommends continuing the rehabilitation program. The cost of the rehabilitation provision, previously estimated in December 2017, has now risen from $526 million to $830 million.

According to ERA, the cost growth is primarily due to an increase in contingency, higher forecast costs related to site services and owners costs, as well as costs associated with tailings transfer to pit 3, additional water treatment, related infrastructure and revegetation requirements.

ERA went on to say that it is reviewing its funding options in light of the increased costs, and that parent company Rio Tinto (ASX:RIO,LSE:RIO,NYSE:RIO) has advised it will work with ERA to help ensure it will be in a position to meet Ranger’s rehabilitation requirements.

“In addition to its funding arrangements, ERA has implemented a business transformation program in order to increase cash flow from identified and new cost saving and productivity opportunities,” the statement reads. “The program aims to generate cash while maintaining the core values of health and safety and continued environmental protection.”

While Ranger has been producing uranium oxide for over 35 years, the project is gradually being moved to closure as its production comes to a simmer. On Friday, the company also released its annual statement of reserves and resources, which shows that Ranger’s proved and probable ore reserves decreased from 5,783 tonnes to 3,735 tonnes last year.

The annual statement also shows Ranger’s mineral resources decreased from 55,135 tonnes to 54,701 tonnes last year. Additionally released Friday were 2018 full-year results, which indicate that uranium oxide production came in at 1,999 tonnes, a 13-percent drop from 2017’s production rate.

ERA saw a net loss of $435 million in 2018 as opposed to 2017’s $44 million; the jump stemmed from the increased costs for Ranger’s rehabilitation provision and a $90-million impairment charge from the company’s undeveloped Jabiluka property.

Additionally, the company stated that its Ranger 3 Deeps exploration project will remain on care and maintenance as it has since 2015 through a “reduced” program.

ERA attributes part of the decision to the state of the uranium market, saying Ranger 3 continues to face material barriers to development and that it is not economically viable without a market turnaround.

The company’s share price was down 4.35 percent on Friday, ending the day of trading at AU$0.33.

Don’t forget to follow us @INN_Resource for real-time updates!

Securities Disclosure: I, Olivia Da Silva, hold no direct investment interest in any company mentioned in this article.

Tempus Closes A $1.9 Million Private Placement

Tempus Resources Ltd (“Tempus” or the “Company”) (ASX:TMR)(TSX.V:TMRR) is pleased to announce that it has closed the non-brokered private placement announced on 23 April 2021 (the “Placement

The Placement has been completed utilising the Company’s available capacity under ASX Listing Rules 7.1 and 7.1A. It includes two tranches: Tranche 1, which consists of 6,037,736 ordinary shares issued on 12 May, 2021, as “Canadian flow-through shares” at a price of C$0.155 (approximately A$0.163) per share for proceeds of approximately C$935,849; and Tranche 2, which consists of 6,065,425 ordinary shares issued on 30 April 2021 at a price of A$0.145 (approximately C$0.138) per share for proceeds of approximately A$879,487. The total proceeds from both Tranche 1 and Tranche 2 of the Placement are approximately A$1,866,149 (C$1,770,042). Following the completion of the Placement, the Company has 98,744,613 shares on issue.

Keep reading... Show less

Galaxy Resources Limited Announcement

Galaxy Resources Limited (ASX: GXY) ( Company ) advises that the following announcement has been made to the Australian Securities Exchange which appears on the Company’s platform (ASX):

  • Appendix 2A

The announcement can be viewed at:

Keep reading... Show less

Massive Sulfide Nickel Drilling Update

Blackstone Minerals Limited (“Blackstone" or the “Company") is pleased provide an exploration update on its flagship Ta Khoa Nickel-Cu-PGE project, for which assay results have been received from drilling at its Massive Sulfide Vein (MSV) prospects (refer Table 3, Table 4 & Appendix 1).

Keep reading... Show less

Novo Completes Malmsbury Option Exercise with GBM Resources Limited

Novo Resources Corp. (“ Novo ” or the “ Company ”) (TSX: NVO & NVO.WT; OTCQX: NSRPF) is pleased to advise that it has completed its option exercise to earn a 50% interest in the Malmsbury gold project (the “ Malmsbury Project ”) held by ASX-listed GBM Resources Limited (ASX: GBZ) (“ GBM ”) following the satisfaction of all conditions precedent, including receipt of Australian Foreign Investment Review Board approval (refer to the Company’s news releases dated March 30, 2020 September 24, 2020 and January 15, 2021 for further details).

“We are thrilled to complete our option exercise at Malmsbury,” commented Dr. Quinton Hennigh, Chairman and President of Novo. “We see Malmsbury as a Fosterville analogue given its similar position along the eastern margin of the prolific Bendigo Zone, epizonal orogenic setting and historic high-grade gold production. Our geologic team will pursue aggressive field work over the next few months with the goal of developing drill targets for testing later this year.”

Keep reading... Show less

Rare Earth Elements Demand is Still Growing

Rare Earth Elements are 17 silvery-white heavy metals with special magnetic capabilities. REEs have diverse applications and are commonly used in lasers, glass, superconductors, hard drives, wind turbine generators, and magnetic materials. Despite the name, REEs are abundant in the world, often found underground alongside uranium in sand structures called monazite. REEs concentrate must first be separated from the sand. Neodymium and praseodymium (NdPr) represent about 80% of the value of REE concentrate. Demand for these elements is growing because of their use in electric vehicles, wind turbines, and appliances. Adams Intelligence expects the demand for NdPr to double in the next five years. Removing REEs from monazite and then separating REEs into individual components is a complicated process. Read More >>

News Provided by Channelchek via QuoteMedia

Keep reading... Show less

Top News

Related News